Change Runcycle offsets
In IWS rule it is possible to change the runcycle offset of IWS application. The IWS rule must change two field in the runcycle.
For positive offset the first is field is field adposoffsets, that must be filled with values with plus operators. The second field is field adrinpos, that must be filled with number of values from the field adposoffsets.
Example: Change runcycle WOCHE positive with one positive offset
For negative offsets the first is field is field adnegoffsets that must be filled with values with plus operators. The second field is field adrinneg, that must be filled with number of values from the field adnegoffsets.
Example: Change runcycle WOCHE with three negative offsets
Last updated